High Visibility Automated Gates

Automated warning signage

USA

    Canada

      International

        Hwy-40 West Rehab., QC

        Location

        Montreal, QC, Canada

        Installation

        Temporary

        Type

        Reversible Counterflow

        About this project

        Trans-Canada Highway (A-40) is one of the two major connections between Montreal and Quebec City. In 2010 the Quebec Ministry of Transportation started the full reconstruction of the Highway between Charles-de-Gaulle Bridge and Henri-Bourassa Boulevard. The worksite used 1,5km of concrete moveable barriers to secure a counterflow on the eastbound (2010) and on the westbound (2011). This counterflow ensured that 3 lanes of traffic were available in each direction during peak hours. As this work site required extensive traffic control, the Ministry opted for automated signage and automated gates to open and close lanes on a daily basis.

        challengeicon

        Challenge

        • Extensive traffic operations (repetitive and time consuming)
        • Safety concern about traffic operations conducted in winter conditions
        • Looking for solution that will reduce traffic control costs
        • Looking for an efficient traffic control solution that will allow more  time to the  contractor to work at nigth

        Solution

        The multiple daily lane closures and openings were conducted with maximum safety using SwiftSign and SwiftGate modules, installed at both ends of the moveable barrier. Each lane closure and lane opening was activated from a safe location using a handheld remote control. As the worksite phasing changed, SwiftSign and SwiftGate solar powered modules were simply relocated.

        solutionicon

        benefiticon

        Benefits

        • Increased traffic operation efficiency allowing more work time for the contractor
        • Increased overall operation safety
        • Reduced road interventions
        • Reduced roadway workers exposure to live traffic
        • Reduced traffic control costs

        Project photo gallery